The Normanby Street reconstruction project will deliver improved safety and efficiency for road users and improved connectivity of pedestrian and cycle pathways in the Yeppoon Central Business District.

The project involves a full reconstruction of Normanby Street between Mary and Park Streets and includes:

  • Trunk water main replacement
  • Water reticulation main replacement
  • Underground power
  • Stormwater upgrades
  • Roundabouts at Mary and Park St intersections
  • New kerb and channel
  • New pavement and asphalt
  • Formalised parking spaces
  • Formal bike lanes
  • New wider footpaths
  • Pedestrian crossings
  • Street lighting
  • Landscaping

December 2024 Project Update

The next construction phase on the Normanby St Reconstruction Project is scheduled to commence in February 2025. This will include construction work on underground services, which is estimated to carry through to September 2025. Once the underground works are completed, roadworks will commence and carry through until 2027.

Construction of underground services is currently in the design phase and the initial planning stages of construction works.

Council is committed to limiting the impact on pedestrian access to businesses/homes as well as limiting the impact on traffic flow and parking during the many stages of construction. When unavoidable impacts occur (so that Council can maintain efficient and safe construction practises), the Project Manager will inform those affected either in person or by letterbox drop prior to works commencing*.

*Two weeks’ notice of works will generally be given, however, in some circumstances this may not be possible due to changes in scheduling and unpredictability when completing underground work (constructing new, renewing and augmenting underground services). Council will also be relying on the availability of other service providers (e.g. Ergon Energy) to complete certain parts of the works, and these schedules may change at short notice.

Design diagram of the Normanby Street Reconstruction project

Design diagram of the Normanby Street Reconstruction project current as at September 2024.


Provide a short summary of your question.

You have 150 characters left

Provide detailed information relating to your question.

You have 500 characters left

Select a respondent from the list that you would most like to answer your question.

Moderation Policy

These are the people that are listening and responding to your questions.

LSC Infrastructure Services

{{ question.username }} asked

{{question.description}}

{{ answer.respondent.name }}
| Edited

Answer this question

Select the respondent who will be marked as answering the question

Provide the answer to the question. Answer can be saved as draft and published when complete.

No questions found